393 Eagle Lane  April/May 2021

5.26.21 Rain has been an unwelcomed visitor for the last couple weeks along with concrete and lumber shortages. It has wreaked havoc in the schedules and progress of construction for this job. We finally were able to start framing but progress was slowed with supply shortages including backorders on windows, soffit and Woodtone 1x6 ceiling. We are down to two windows on backorder then the painter starts along with the mechanicals.